• OUr First Completed Shopfront

Our Priority Projects

At the start of the scheme a number of projects were given priority.

You can see progress and detail of each project by clicking on the relevant picture – this page is a work in progress and will be regularly updated.

HIgh Priority Projects
Address:Appearance Pre-CARSUse Pre-ProjectType of WorksFinal UseProgress
1 Saltoun SquareTown Chambers and Former Police StationFull Restoration and Re-UseThe Faithlie Centre –

Council Services and Public Space

 

Complete
5-13 Mid StreetJohn Trail’s Bookshop (unused after fire)Full Restoration and Re-UseHotel and RestaurantIn Progress
9-11 Frithside StreetPrivate Offices (Brown & Macrae Solicitors)Repair and Restoration worksunchangedIn Progress
51-55 Broad StreetShops with Flats aboveRepair and Restoration worksunchangedPending
1-7 Frithside StreetShopfront with Flats aboveRepair and Restoration worksunchangedIn Progress
Medium Priority Projects
AddressAppearance Pre-CARSUse Pre-ProjectType of WorksFinal UseProgress
16-20 High StreetShopfronts with flats aboveShopfront Restoration, windows, rainwater goodsunchangedPending
21-31 Commerce Street

 

ShopfrontsRestoration of Flat Roofs and facadesunchangedIn Progress
22 – 30 High StreetShopfronts with flats aboveConserve the exterior, repainting of timberwork and metalwork including shopfront.unchangedIn progress
23, High StreetShopfrontReplacement of modern shopfront with traditional timber designunchangedIn progress
17-21 High StreetShopfronts with flats aboveConserve the exterior, repainting of timberwork and metalwork including shopfront.unchangedPending